Project Plans and Schedule

Project Plans and Schedule

Stage 1 Plans were submitted to ODOT for review and comment.  Stage 1 plans generally detail the line, grade and typical cross sections of the proposed improvements.  ODOT comments have been received and are being addressed.

Stage 2 Plans are being prepared for an April 2025 submittal. These plans generally include:

  • Survey details
  • Plan and profile sheets with existing topography
  • Construction limits
  • Grading
  • Intersection details
  • Water and sewer work
  • Pavement and signing plan
  • Signal plans
  • Maintenance of traffic plan with sequence and phasing
  • Utility correspondence
  • Right-of-way plan sheets
  • Environmental documents
  • Geotechnical report and profiles
  • Updated cost estimate and updated construction schedule.

Stage 3 Drawings are due in August 2025 which are the +/-90% complete plan set with specifications and estimate. Final Plans, Specifications, and Estimate are due October 2025, and Construction Advertisement, Bid, and Award will take place from December 2025 to March 2026.

Estimated Construction Schedule

Phase 1 (Lakewood Hts Blvd to Franklin Blvd) – April 2026 to April 2027

Phase 2 (Franklin Blvd to Clifton Blvd) – May 2027 to November 2028